How deep are utility lines buried? Gas, electric, water and fiber depths — and a “Can I dig here?” check
Updated
The short answer
By code, a gas service line needs at least 12 in of cover on private property and a gas main 24 in; direct-burial electric cable 24 in, PVC conduit 18 in and a GFCI-protected 120 V yard circuit 12 in; a water line 12 in and below the frost line. Phone, cable and fiber drops have no national minimum. Real lines are often shallower than code, so call 811 and hand dig near the marks.
How urgent · It depends
Code depths are minimums at installation, not a promise about your yard. Whatever the depth, the safe order is the same: call 811, wait for the marks, and hand dig inside the tolerance zone.
Step 1, whatever the depth: call 811
Call 811 or file a request online before you dig — it’s free. Allow a few working days for the marks. Then hand dig near any mark — no power auger or machine there.
At 24 in, these could be in your hole even if installed to code
Low-voltage landscape lighting or irrigation control wire (30 V or less)
6 in of cover, or less where a listed low-voltage lighting system's instructions allow (NEC Table 300.5, column 5). Private wiring, often laid just under mulch — 811 won't mark it.
Private — 811 won't mark it
Electric cable in metal conduit
6 in of cover for rigid metal or intermediate metal conduit (NEC Table 300.5). Usually a private circuit you or a previous owner had installed — 811 won't mark it.
Private — 811 won't mark it
Residential 120 V circuit, GFCI-protected, 20 A or less
12 in of cover for a residential 120 V branch circuit of 20 A or less with GFCI protection (NEC Table 300.5). The usual way a yard light, shed or pump circuit is run. Private — 811 won't mark it.
Private — 811 won't mark it
Electric cable in PVC conduit
18 in of cover for nonmetallic (PVC) conduit not encased in concrete (NEC Table 300.5). Private wiring is not marked by 811.
Private — 811 won't mark it
Direct-burial electric cable (UF)
24 in of cover for direct-burial cable or conductors (NEC Table 300.5). Private wiring is not marked by 811. The utility's own service line to your meter is marked.
Private — 811 won't mark it
The power company's underground service to your meter
Set by the utility, not the NEC; 24 in of cover for secondary service in the published specs we checked (Utility service rules (PG&E Greenbook, Snohomish County PUD, Clark Public Utilities)). 811 marks it. Primary (higher-voltage) cable is deeper — PG&E asks for 30 in.
811 marks it
Gas service line (the main to your meter)
12 in of cover on private property, 18 in in streets and roads (49 CFR 192.361). 811 marks the utility's service line. A line from the meter to a grill, heater or outbuilding is yours and isn't marked.
811 marks the utility's part only
Gas main (usually under the street or easement)
24 in of cover for a buried main, less where rock or other conditions are approved (49 CFR 192.327). Rarely in a back yard, but common along a front property line or easement.
811 marks it
Water service line
At least 12 in deep and 6 in below the frost line (IPC/IRC); 12 in below frost under the UPC (IRC P2603.5). The utility's part up to the meter or curb stop is marked; the line from there to the house usually isn't.
811 marks the utility's part only
No national minimum depth — could be at any depth
Sewer lateral
No national minimum; set locally, and shallowest where it leaves the house (IPC 305.4.1 (left to each jurisdiction)). Your private sewer lateral is usually not marked by 811. A plumber or private locator can find it.
Private — 811 won't mark it
Phone, cable TV or fiber drop
No national minimum for a house drop; set by the provider and local right-of-way rules (Provider and local rules). Drops are often the shallowest line in a yard. One Texas fiber provider asks for 15 in of cover in soil; Carmel, Indiana, had to pass a rule requiring new lines to be at least 6 in down.
811 marks it
Sprinkler or irrigation line
No code minimum; laid by whoever installed the system (None). Private — 811 won't mark it. Lateral lines in home systems are commonly 8–10 in deep, mains deeper.
Private — 811 won't mark it
Health & safety
Hitting a gas or electric line can kill. If you smell gas or damage a line, leave the area, then call 911 and the utility from a safe distance. Don't try to fix or cover a damaged line.
Burial depth by type of line
The minimum cover each line must have when it is installed, the rule that sets it, and whether 811 will mark it. Cover is measured from the top of the pipe or cable to finished grade.
| Line | Minimum cover | Rule | Marked by 811? |
|---|---|---|---|
| Low-voltage landscape lighting or irrigation control wire (30 V or less) | 6 in | 6 in of cover, or less where a listed low-voltage lighting system's instructions allow (NEC Table 300.5, column 5) | No — private |
| Electric cable in metal conduit | 6 in | 6 in of cover for rigid metal or intermediate metal conduit (NEC Table 300.5) | No — private |
| Residential 120 V circuit, GFCI-protected, 20 A or less | 12 in | 12 in of cover for a residential 120 V branch circuit of 20 A or less with GFCI protection (NEC Table 300.5) | No — private |
| Electric cable in PVC conduit | 18 in | 18 in of cover for nonmetallic (PVC) conduit not encased in concrete (NEC Table 300.5) | No — private |
| Direct-burial electric cable (UF) | 24 in | 24 in of cover for direct-burial cable or conductors (NEC Table 300.5) | No — private |
| The power company's underground service to your meter | 24 in | Set by the utility, not the NEC; 24 in of cover for secondary service in the published specs we checked (Utility service rules (PG&E Greenbook, Snohomish County PUD, Clark Public Utilities)) | Yes |
| Gas service line (the main to your meter) | 12 in | 12 in of cover on private property, 18 in in streets and roads (49 CFR 192.361) | Utility's part only |
| Gas main (usually under the street or easement) | 24 in | 24 in of cover for a buried main, less where rock or other conditions are approved (49 CFR 192.327) | Yes |
| Water service line | 12 in | At least 12 in deep and 6 in below the frost line (IPC/IRC); 12 in below frost under the UPC (IRC P2603.5) | Utility's part only |
| Sewer lateral | No national minimum | No national minimum; set locally, and shallowest where it leaves the house (IPC 305.4.1 (left to each jurisdiction)) | No — private |
| Phone, cable TV or fiber drop | No national minimum | No national minimum for a house drop; set by the provider and local right-of-way rules (Provider and local rules) | Yes |
| Sprinkler or irrigation line | No national minimum | No code minimum; laid by whoever installed the system (None) | No — private |
Minimums at installation, not where a line is today. Electrical figures are the 2020 NEC’s ordinary-yard row; under a house driveway most rise to 18 in. Your state or city may adopt a different edition or add its own rules.
Why your lines may not be at code depth
Every depth in the table below is a minimum cover at the time the line went in, measured from the top of the pipe or cable to the finished grade. Grade doesn't stay finished. A yard gets regraded for a patio, topsoil is scraped for a lawn, a slope erodes, roots heave the soil, and a line laid at 24 inches can end up at 12. The 811 system's own homeowner guidance says erosion and root growth can change a line's depth and location, and that some utilities sit just inches below the surface.
Private lines are the bigger unknown. The wire to a lamp post or shed, a gas line to a grill, an invisible dog fence or a sprinkler system was laid by whoever installed it, often with no inspection — and 811 doesn't mark them. Michigan's one-call center tells homeowners that locators mark only the approximate location, never the depth, and that exact depth can't be determined because of human interference and weather.
What 811 marks — and what it doesn't
When you call 811, the utilities that have lines near your dig site send locators to paint or flag them. They mark the lines they own: gas mains and services up to the meter, the power company's cable to your meter, the water utility's line to the meter or curb stop, phone, cable TV and fiber.
They don't mark anything you own. Typical private lines include electric circuits to outbuildings, lamp posts and pools, gas piping from the meter to a grill or heater, sprinkler pipe and its control wire, pet fences, and usually your sewer lateral and the water line from the meter to the house. A private locator finds those for a fee; a plumber with a camera and sonde can trace a sewer lateral.
The tolerance zone: where you hand dig
A mark shows the approximate location, not the exact line. Every state sets a tolerance zone either side of the mark — commonly 18 or 24 inches beyond the outside edge of the line, but it varies (see the state table below) — inside which you expose the line by hand or with vacuum excavation before any power tool goes near it. The national 811 site tells homeowners to avoid digging on top of or within 18–24 inches on all sides of the marks.
Hand digging means a round-point shovel used gently, prying soil rather than stabbing it, and stopping as soon as you see the line or a warning tape. A fence post auger, a trencher or a tree spade inside the zone is exactly how most homeowner hits happen.
How deep are gas lines buried?
Federal pipeline rules set the minimum. A gas service line — the pipe from the main to your meter — must have at least 12 in of cover on private property and 18 in in streets and roads (49 CFR 192.361). A gas main needs 24 in (49 CFR 192.327), though state or local law can allow less where it meets federal conditions. Larger transmission pipelines need 30 to 36 in in normal soil, depending on how built-up the area is.
Where an underground structure gets in the way, both rules allow less cover with extra protection. And the federal rule stops at your meter: a gas line from the meter to a grill, pool heater or detached garage is house piping, laid by a plumber, and 811 won't mark it.
How deep are electrical lines buried?
For wiring on your side of the meter, the National Electrical Code's Table 300.5 sets cover by wiring method. In the 2020 edition, for ordinary yard locations: direct-burial cable such as UF needs 24 in; PVC conduit 18 in; rigid or intermediate metal conduit 6 in; a residential 120 V branch circuit of 20 A or less with GFCI protection 12 in; and landscape lighting or irrigation control wiring of 30 V or less 6 in. Under a house driveway most of these rise to 18 in; under streets and parking lots, 24 in.
The power company's own underground service to your meter isn't covered by the NEC — each utility sets its depth. The specs we checked from PG&E, Snohomish County PUD and Clark Public Utilities all ask for 24 in of cover for secondary service, with PG&E asking 30 in for higher-voltage primary cable.
How deep are water and sewer lines buried?
Water lines follow the frost line. The International Residential and Plumbing Codes put a water service at least 12 in deep and 6 in below the local frost line; the Uniform Plumbing Code asks for 12 in below frost. That is a foot in the Gulf states and five feet or more in the northern plains — our water line page gives the depth for any zip code, and FenceLevel's frost line map shows the frost depth itself.
Sewer laterals have no national depth. They start shallow where they leave the house and get deeper toward the street because they must keep falling, and local minimums range from 18 in of cover in Kentucky to 42 in in Michigan.
How deep are fiber optic, phone and cable lines buried?
There's no national minimum for a buried phone, cable TV or fiber drop to a house — the provider and the local right-of-way rules set it, and drops are often the shallowest line in a yard. One Texas fiber provider asks customers who dig their own conduit trench for 15 in of cover in soil. Carmel, Indiana, passed a 2024 ordinance requiring new telecom lines to be buried at least 6 in, after complaints about lines left just under the turf. Treat any of them as possibly within a spade's depth.
Sprinkler and irrigation lines
No code sets their depth. Lateral pipes in home irrigation systems are commonly laid 8–10 in deep, with the pressurised mainline deeper, and the low-voltage control wire runs alongside. They're private, so 811 won't mark them — the installer's drawing, the valve boxes and the sprinkler heads are your best guide.
Digging for a fence, a drain or a tree
A fence post hole is narrow but deep: a third of the fence's above-ground height, and below the frost line where that is deeper, which puts many posts at 24–48 in — past the cover of nearly every line in the table. A yard French drain trench is typically about 18 in deep and runs for tens of feet, so it crosses lines rather than missing them. A tree hole only goes as deep as the root ball but two to three times as wide. Garden beds and sprinkler trenches are shallow, but so are pet fences, low-voltage wire and telecom drops.
Each of these needs an 811 ticket. Most state laws apply to any excavation, including digging by hand.
811 rules by state: notice, tolerance zone and ticket life
How far ahead you must call, how wide the hand-dig zone is either side of a mark, and how long the marks stay valid — from each state’s law, its one-call center or PHMSA’s state summary, with the source for every row. Checked October 17, 2026.
| State | Notice before digging | Tolerance zone | Ticket life | Source |
|---|---|---|---|---|
| AlabamaAla. Code § 37-15 (revised law takes effect Jan 1, 2027) | 2 working days (no more than 10), not counting the day of notice | Facility width plus 18 in each side | 20 working days | [1] |
| AlaskaAlaska Stat. § 42.30.400–.410 | 2 working days (no more than 15) | Marks within 24 in for lines 10 ft deep or less | 15 working days (update by the 13th working day to keep it active) | [1][2][3] |
| ArizonaA.R.S. § 40-360.21–.22 | 2 working days (operators must mark within 2 working days) | Expose by hand within 24 in of a marked facility | 15 working days from marking | [1][2] |
| ArkansasArk. Code § 14-271-101 et seq. (updated 2025) | 2 working days (utilities' time to locate) | Facility width plus 18 in each side | 20 working days | [1][2] |
| CaliforniaCal. Gov. Code § 4216 et seq. | 2 working days, not counting the day of notice (no more than 14 calendar days) | 24 in each side of the field marking | 28 days | [1][2] |
| ColoradoC.R.S. § 9-1.5-103 | 3 business days (Colorado 811; an older statute copy says 2) | 18 in from the sides of a marked facility | 30 calendar days after the locate due date | [1][2] |
| ConnecticutConn. Gen. Stat. § 16-345 et seq. | 2 full working days, excluding the day of the call | 18 in either side of the facility | 30 days from the notice | [1][2] |
| DelawareDel. Code tit. 26, § 801 et seq. | 3 business days (no more than 12) | 24 in from the outside wall or edge | 12 business days | [1] |
| District of ColumbiaD.C. Code § 34-2704 | 96 hours, excluding weekends and holidays (no more than 10 days) | Hand dig within 18 in of the outermost part of the facility | 15 days, excluding weekends and holidays | [1] |
| FloridaFla. Stat. ch. 556 | 2 full business days | 24 in from either side of a marked facility | 30 calendar days | [1] |
| GeorgiaO.C.G.A. § 25-9 | 2 business days (no more than 8), counted from 7 a.m. the business day after the request | Facility width plus 18 in each side | 30 calendar days | [1] |
| HawaiiHaw. Rev. Stat. ch. 269E | 5 working days (no more than 28 calendar days) | 30 in either side of the facility | 28 calendar days | [1][2] |
| IdahoIdaho Code § 55-2201 et seq. | 2 business days (no more than 10) | 24 in of the facility's outside dimensions | 4 weeks from notification | [1][2] |
| Illinois220 ILCS 50 | 2 days (no more than 10), excluding weekends, holidays and the day of submission | 18 in either side of a marked line | 25 days | [1][2] |
| IndianaInd. Code § 8-1-26 | 2 full working days (no more than 10 calendar days) | Facility width plus 2 ft | 20 days | [1] |
| IowaIowa Code ch. 480 | 48 hours from 6 a.m. the next business day, excluding weekends and holidays | 18 in either side of the facility | 25 calendar days | [1] |
| KansasK.S.A. 66-1801 et seq. | 2 full working days | 24 in of the facility's outside dimensions | 20 calendar days | [1][2] |
| KentuckyKRS 367.4901–367.4917 | 2 full working days (no more than 10) | Facility width plus 24 in | 21 calendar days | [1] |
| LouisianaLa. R.S. 40:1749.11 et seq. | 48 hours (no more than 120), excluding weekends and holidays | Facility width plus 18 in each side | 20 calendar days | [1][2] |
| Maine23 M.R.S. § 3360-A | 3 business days (no more than 30 calendar days) | No mechanical digging within 18 in of marks | Start within 30 days of notice | [1] |
| MarylandMd. Code, Pub. Util. § 12-101 et seq. | 3 business days (no more than 12) | Hand expose within 18 in of a marking | 12 business days after the start date | [1][2] |
| MassachusettsM.G.L. c. 82, §§ 40–40E | 72 hours, excluding weekends and holidays (no more than 30 days) | Facility width plus up to 18 in each side | 30 days (Dig Safe) | [1][2][3] |
| MichiganMCL 460.721 et seq. | 72 hours, excluding non-business days (no more than 14 calendar days) | 48 in caution zone either side of the marks | 21 days from the start date | [1][2] |
| MinnesotaMinn. Stat. § 216D.04 | 48 hours, excluding the day of notice, weekends and holidays (no more than 14 days) | 24 in of the marked location | 14 calendar days | [1] |
| MississippiMiss. Code § 77-13-1 et seq. | 3 working days (no more than 10) | 18 in from each side of the facility | 14 calendar days | [1] |
| MissouriRSMo § 319.010 et seq. | 2 working days (no more than 10) | Facility width plus 24 in each side | Relocate if work doesn't start within 10 working days | [1][2] |
| MontanaMCA 69-4-501 to 503 | Before digging; owners mark within 2 business days | 18 in either side of the facility | 30 days after marking | [1][2] |
| NebraskaNeb. Rev. Stat. 76-2321, 76-2323 | 2 full business days (no more than 10) | 18 in either side of the marking | Not set; excavation must start within 17 days of the noticed start date | [1][2] |
| NevadaNRS 455; NAC 455.165 | 2 working days (no more than 28 calendar days) | 24 in either side of the facility | 28 calendar days | [1][2] |
| New HampshireRSA 374:51 | 72 hours, excluding weekends and holidays (no more than 30 days) | Facility width plus 18 in each side (Dig Safe) | 30 calendar days | [1][2] |
| New JerseyN.J.S.A. 48:2-73; N.J.A.C. 14:2-3 | 3 business days (no more than 10) | 24 in from the outside wall of the facility | 45 business days | [1] |
| New MexicoNMSA ch. 62, art. 14; 18.60.5 NMAC | 2 full working days, not counting the day of the call | 18 in | 15 working days | [1] |
| New York16 NYCRR Part 753 | 2 working days (no more than 10), not counting the day of the call | 24 in either side of the center line, plus half the diameter | No fixed expiry in Part 753; give new notice if the start slips more than 10 working days | [1] |
| North CarolinaN.C.G.S. ch. 87, art. 8A | 3 full working days | 24 in either side of the center line, plus half the diameter | 28 calendar days after the work start date | [1] |
| North DakotaN.D.C.C. ch. 49-23 | 48 hours from 12:01 a.m. the next day, excluding weekends and holidays | 24 in of the outer edges of the facility | 21 days after the planned excavation date | [1] |
| OhioOhio Rev. Code 3781.25–3781.32 | 2 working days, not counting the day of notice (no more than 16 calendar days) | Facility width plus 18 in each side | Not set; renotify if work doesn't start within 16 calendar days | [1][2] |
| Oklahoma63 O.S. 142.6 | 48 hours, excluding the day of notice, weekends and holidays (OKIE811 advises 3 business days) | 24 in either side of the facility | 14 calendar days from the start date | [1][2] |
| OregonORS 757.542–757.562; OAR 952-001 | 2 full business days (no more than 10) | 24 in of the facility's outside dimensions | 30 days (from Jan 1, 2026; previously 45) | [1][2] |
| PennsylvaniaAct 287 of 1974, as amended | 3 business days (no more than 10) | 18 in from the outside wall or edge | No fixed expiry in Act 287; renotify if you leave the site for more than 2 business days | [1] |
| Rhode IslandR.I. Gen. Laws ch. 39-1.2 | 72 hours, excluding weekends and holidays (no more than 30 days) | 18 in either side of the facility | No expiry while marks are maintained | [1][2] |
| South CarolinaS.C. Code ch. 58-36 | 3 to 12 full working days | 24 in either side of the outside edge of the mark | 15 working days after the start date | [1] |
| South DakotaSDCL ch. 49-7A | 48 hours, excluding weekends and holidays | 18 in from the sides of the facility | 21 days (South Dakota 811) | [1][2] |
| TennesseeTenn. Code Ann. § 65-31-101 et seq. | 3 working days (no more than 10) | Facility width plus 24 in each side | 15 calendar days after the legal start date | [1][2] |
| TexasTex. Util. Code ch. 251; 16 TAC ch. 18 | 48 hours, excluding weekends and holidays (no more than 14 days) | 18 in plus half the diameter (Railroad Commission rule for pipelines) | 14 days (Railroad Commission rule) | [1][2][3] |
| UtahUtah Code 54-8a | 48 hours, excluding weekends and holidays (no more than 14 days) | 24 in either side of the outside edge of the mark | 21 calendar days | [1][2][3] |
| Vermont30 V.S.A. ch. 86 | 72 hours, excluding weekends and holidays (no more than 30 days) | 18 in either side of the facility | 30 days | [1][2] |
| VirginiaVa. Code 56-265.14 to 56-265.32 | About 3 working days — lines are marked by 7 a.m. on the third working day | 24 in either side of the mark | 15 working days | [1][2] |
| WashingtonRCW 19.122 | 2 full business days (no more than 10) | 24 in of the facility's outside dimensions | 45 calendar days | [1] |
| West VirginiaW. Va. Code 24C-1 | 48 hours, excluding weekends and holidays (no more than 10 work days) | Marked within 24 in of the facility's outside walls | No expiry (WV811) | [1][2] |
| WisconsinWis. Stat. 182.0175 | 3 working days | 18 in clearance between power equipment and the marked facility | Not set; renotify if work doesn't start within 10 days of the scheduled date | [1] |
| WyomingW.S. 37-12-301 to 307 | 2 full business days (no more than 14) | Marked within 24 in of the facility's sides | 14 business days | [1] |
All 51 jurisdictions (the 50 states and DC) verified. “Working days” usually exclude weekends and legal holidays. Laws change; the one-call center is the authority.
Sources
Each source was opened and read on October 17, 2026. Rules change — the original is the authority.
- 49 CFR 192.361 — service lines: installation (LII) — 12 in cover on private property, 18 in in streets and roadshttps://www.law.cornell.edu/cfr/text/49/192.361
- 49 CFR 192.327 — cover (LII) — 24 in for mains; transmission line cover by class locationhttps://www.law.cornell.edu/cfr/text/49/192.327
- NEC 2020 Table 300.5, reproduced in the Town of Woodbury, CT, electrical handout — minimum cover by wiring methodhttps://woodburyct.org/vertical/Sites/%7B59751637-3DF2-41D3-B20A-866E470B1D1D%7D/uploads/2020_Inground_Pool_Electrical.pdf
- PG&E Greenbook, UG-1 General (Doc. 038193) — 24 in secondary, 30 in primary coverhttps://PGE.com/assets/pge/docs/account/service-requests/038193.pdf
- Snohomish County PUD, Electric Service Requirements — underground service — 24 in minimum cover for secondary servicehttps://esr.snopud.com/Content/4_ug/4_UG_Svc.htm
- Clark Public Utilities, Residential Handbook — 24 in of coverhttps://www.clarkpublicutilities.com/building-remodeling/residential-handbook
- GVTC, Buried Service Requirements — 15 in cover in soil for a customer-dug fiber conduit trenchhttps://gvtc.com/support/installation/buried-service-requirements
- Current Publishing, Carmel requiring telecommunication cables be buried at least 6 inches (2024) — news report of the ordinancehttps://youarecurrent.com/2024/09/04/carmel-requiring-telecommunication-cables-be-buried-at-least-6-inches-below-ground
- IrrigationTutorials.com, irrigation pipe depth — practitioner guide: laterals about 8–10 inhttps://irrigationtutorials.com/?p=2114
- 811 Before You Dig (Common Ground Alliance) — before you dig — erosion and roots change depth; some lines just inches downhttps://811beforeyoudig.com/before-you-dig/
- 811 Before You Dig — for homeowners — avoid digging within 18–24 in of markshttps://811beforeyoudig.com/for-homeowners/
- MISS DIG 811 (Michigan), homeowner FAQ — depth isn't marked; private lines aren't markedhttps://www.missdig811.org/homeowners/faq.html
- OHIO811, homeowners — hand digging also requires noticehttps://oups.org/Homeowners/
- Loudoun Water, private utility lines — examples of private lines 811 won't markhttps://www.loudounwater.org/node/1300
- International Society of Arboriculture, planting a tree — hole only as deep as the root ball, 2–3 times as widehttps://www.treesaregood.org/treeowner/plantingatree
- FenceLevel, how deep should fence posts be — the one-third rule and frost depthhttps://www.fencelevel.com/learn/how-deep-should-fence-posts-be
- YardDrainageFixes, how to install a French drain — typical trench depthhttps://www.yarddrainagefixes.com/solutions/install-yard-french-drain
- FenceLevel, frost line depth by zip code — frost depth that sets water line depthhttps://www.fencelevel.com/frost-line-depth-by-zip-code
Frequently asked questions
- How deep are gas lines buried?
- A gas service line to a house needs at least 12 in of cover on private property and 18 in under streets (49 CFR 192.361); a gas main 24 in (49 CFR 192.327). Grade changes can leave a line shallower, and gas piping beyond your meter isn't marked by 811.
- How deep is a gas line buried in a residential yard?
- The utility's service line is required to have 12 in of cover on private property at installation — but regrading and erosion can change that, so assume it could be shallower and hand dig near the marks.
- How deep are electrical lines buried?
- Under NEC Table 300.5: 24 in for direct-burial cable, 18 in in PVC conduit, 6 in in rigid metal conduit, 12 in for a GFCI-protected 120 V, 20 A residential circuit, and 6 in for 30 V landscape lighting. The power company's service line is commonly 24 in.
- How deep are fiber optic lines buried?
- There's no national minimum for a fiber drop to a house. Providers set their own, and drops are often only inches deep — one Indiana city had to require at least 6 in for new lines. Call 811; your provider's line will be marked.
- How deep are water lines buried?
- At least 12 in deep and 6 in below the local frost line under the IPC and IRC — anywhere from about a foot in warm states to five feet or more in the coldest. Our water line page gives the depth by zip code.
- Do I need to call 811 to dig a fence post or plant a tree?
- Yes. State one-call laws generally cover any digging, including by hand, and the 811 system asks homeowners to call for every project regardless of depth. It's free.
- Does 811 mark sprinkler lines and private electric lines?
- No. 811 marks lines owned by the utilities. Sprinkler systems, pet fences, wiring to sheds and lamp posts, gas piping past the meter and usually your sewer lateral are private — hire a private locator to find them.
- Does 811 tell you how deep the line is?
- No. Locators mark the approximate horizontal location, not the depth. That's why every state requires hand digging within the tolerance zone either side of the marks.